GRAHAM Construction will be commencing work towards the end of May 2026 and you will start to notice activity on the site.
The GRAHAM site team is always on hand to help. Please contact them at any time if you have questions or concerns, or would like any further information:
Samantha Swain, Resident Liaison Officer
Email: buildingsouthcustomerrelations@graham.co.uk
Tel: 07391 185430
Tel: 02895 071 034 (24/7 customer care team – for out of hours emergencies only)
The first works will be in St Georges Way (Phase 1 of the Agora Project) and Church Street are scheduled to commence on 18 May 2026.
The scope of initial works will include:
• Demolition of the garages located behind 31–36 St Georges Way
• Excavation of existing roads and parking areas St Georges Way and
• Installation of new hard and soft landscaping in line with the approved plans
• New hoarding installation to the main Agora site and ground work preparation
We appreciate your patience and understanding while these works are carried out. We are committed to keeping you informed and minimising disruption wherever possible, although inevitably there will be an increase in large vehicular traffic. Our site hours will be 8am to 6pm Monday to Friday, and 8am to 1pm on Saturdays. Should you have any concerns or require assistance, please do not hesitate to get in touch.